WORK TO preserve one of Limerick’s top tourist attractions is under way.
Engineers have moved in to Clancy’s Strand to begin the operation to restore the pedestal under the Treaty Stone, which has been weather damaged.
In a project set to take up to eight weeks, all growth and vegetation on the monument is to be removed.
Natural hydraulic lime mortar is to be used to rake out and repoint the structure, stone indentation will also take place. Resin injections will see the cracked stone repaired, while the bronze inset of the historic construction will be cleaned.
Bricks will be cleaned, while brick paving will be raked out and re-pointed, a council spokesperson said.
The last piece of the job – which is dependent on clement weather – will be a final clean down of the area when scaffolding is removed from the site.
Nolan Group is the main contractor on the project, while the conservation consultant Carrig Conservation International has specified the works which need to take place.

Outgoing City North councillor John Costelloe is delighted the work is under way.
“I've been chasing this for a number of years. It's invaluable to Limerick. I welcome the fact work has commenced. It's the jewel in Limerick's crown and I'm so glad it's being restored,” he said.
The Treaty Stone is the rock which the Treaty of Limerick was signed in 1691, heralding an end to the Williamite War.
Subscribe or register today to discover more from DonegalLive.ie
Buy the e-paper of the Donegal Democrat, Donegal People's Press, Donegal Post and Inish Times here for instant access to Donegal's premier news titles.
Keep up with the latest news from Donegal with our daily newsletter featuring the most important stories of the day delivered to your inbox every evening at 5pm.