Decision made over controversial wind farm in Limerick

There was opposition to the planned wind farm in south Limerick (stock image)placeholder image
There was opposition to the planned wind farm in south Limerick (stock image) | Iconic

More than 60 groups and individuals had expressed concern at wind energy plan

AN Coimisiún Pleanála has approved plans for a new wind farm in Limerick.

It comes despite more than 60 submissions to the proposed development in the Bruree, Charleville and Effin-Garrienderk area.

Energy firm Garrane Green Energy sought permission to construct nine wind turbines, a grid connection and other works across the townlands of Garrane, Creggane and Ballynagoul in the south of the county.

In a decision published this week, the national planning appeals body ruled seven of the proposed nine wind turbines can be built across the townlands. It has decided to exclude two turbines with the planning authority ruling this is in the interest of the protection of the bird and bat habitat in the area.

Among the groups and individuals to object to the plans were councillors Brigid Teefy, PJ Carey in Cappamore-Kilmallock and John O'Donoghue, Adare-Rathkeale.

Also expressing concerns was Independent Ireland TD Richard O’Donoghue and Sinn Fein Senator Joanne Collins.

The Bruree-Charleville-Effin Wind Farm Action Group lodged a 277-page objection against the development.

The group says the project would have unacceptable impacts on local wildlife and biodiversity, is being developed on a flood-prone site, would cause excessive disruption to residents through noise, shadow flicker, traffic and visual intrusion, and has failed to properly assess risks to local roads, bridges and archaeological heritage.

For its part, Garrane Green Energy said the proposed wind farm site has been designated by council as a preferred area for wind energy development.

"The proposed Garrane Green Energy project will play a key role in supporting our national climate targets, which include reducing greenhouse gas emissions by 51% by 2030 and achieving net-zero emissions by 2050,” the firm said.

They also said the project has the potential to provide clean power for up to 30,000 homes across Limerick and cut carbon emissions by 46,500 in each year of operation.

An Coimisiún Pleanála ruled on the application due to its size and scale, but it was also fast-tracked through the planning process under new renewable energy legislation, which guarantees a decision within 12 months from the lodging of planning papers.

Planners have ruled the turbines can tower up 170-metres, with the rotor diameters stretching out 150 metres. Permission is in place for 35 years from the date the windfarm is commissioned. After this, all structures will need to be removed from site unless there is a further extension given.