Limerick Tunnel guarantee clause to cost taxpayer €4.7m this year

The Comptroller and Auditor General has predicted the Limerick Tunnel will rely on state subvention until 2041

The Comptroller and Auditor General has predicted the Limerick Tunnel will rely on state subvention until 2041

THE LIMERICK Tunnel will continue to rely on state subvention for the next 30 years, the state spending watchdog has predicted.

The Comptroller and Auditor General’s report finds that under a revenue guarantee clause, €5.2 million was shelled out by taxpayers in 2011 to the operators of the Limerick Tunnel and a second tolled PPP road - the M3 Kells to Clonee scheme. That figure is likely to rise to €6.7 million for the two roads in 2012.

Sean O’Neill, National Roads Authority, told the Limerick Chronicle that of the projected payout in 2012, around €4.7 million related to the Limerick Tunnel scheme. These figures were a “worst-case scenario” projected over the next 30 years.

“Unfortunately, that’s where we are right now because the traffic levels are so low. We are not thrilled about it but it is where it is,” Mr O’Neill said.

“On the plus side, the Mid-West still has a fantastic piece of infrastructure that benefits the economy.”

Around €180 million of the €600 million costs of the Limerick Tunnel scheme were met by the state, with the remainder met by the Direct Route consortium which will continue to collect toll revenue until 2041.

The NRA has previously explained that built in to the PPP contract was a revenue guarantee clause where the state would compensate Direct Route if traffic fell short of projections. This reflected the risk the private consortium was taking on in financing the scheme.

And with the tunnel having opened in the middle of the recession two years ago, traffic has yet to meet the levels hoped for when the contract was agreed. And this, according to the C&AG’s report, is likely to remain the case for the entire duration of the concession.

“The Limerick Tunnel contract provides for a 6% increase in the 2012 level of traffic over 2011. Subsequent increases are smaller but continue until 2035, after which the traffic guarantee will remain unchanged,” the C&AG report states.

A graph in the report shows the projection for 2012 is about 5,000 motorists per day short of what was originally hoped for.

It is currently assumed that traffic volumes for the scheme will increase at 2.5% per annum.

Based on that modest growth assumption, “the projected traffic levels using the Limerick Tunnel will not reach the guaranteed traffic levels and the State will make additional payments to the PPP company for the whole duration of the contract (i.e. until 2041),” the C&AG report finds.


 
Find It

"Business owner? - Claim your business and Advertise with us"

In association with qype logo

Looking for...

Featured advertisers

Jobs

Search for a job

Weather for Limerick

Thursday 23 May 2013

5 day forecast

Today

Sunny spells

Sunny spells

Temperature: 6 C to 13 C

Wind Speed: 25 mph

Wind direction: North west

Tomorrow

Sunny spells

Sunny spells

Temperature: 7 C to 15 C

Wind Speed: 18 mph

Wind direction: North west

Press Complaints Commission

This website and its associated newspaper are full participating members of the Press Council of Ireland and supports the Office of the Press Ombudsman.  This scheme in addition to defending the freedom of the press, offers readers a quick, fair and free method of dealing with complaints that they may have in relation to articles that appear on our pages.  To contact the Office of the Press Ombudsman go to
www.pressombudsman.ie or www.presscouncil.ie

Limerick Leader provides news, events and sport features from the Limerick area. For the best up to date information relating to Limerick and the surrounding areas visit us at Limerick Leader regularly or bookmark this page.